City Planner
Plan Prairie City’s heat, cars and rooftop solar, run its energy hub hour by hour against each district’s substation limit, and see what changes for each household group
The brief
- The city
- Prairie City (fictional): 250,000 people in a dense core, suburbs and a rural fringe, each behind one substation (a teaching simplification); 2025's homes, prices and eight representative days.
- You decide
- How many furnaces become heat pumps; retrofits; a district-heat network in the core; electric cars (EVs) and how they charge; rooftop solar; batteries; whether substations may be upgraded.
- The engine works out
- A linear program (LP) runs the city's energy hub hour by hour at the least cost, each hour within each substation's limit, and buys upgrades only where the busiest hour needs them.
- Who pays
- Bills by household group and their energy burden: home energy bills as a share of income. Groups are bands of area median income (AMI).
- It leaves out
- Power flow inside a district, outages, growth to 2040, the cars' prices, and how bills are really set: the household table is a screening estimate, not an output of the LP.
Open-ended: start from a preset, change one thing at a time, and copy the plan link to keep a plan. Prairie City is fictional; its numbers are illustrative.
Siting with map layers is in the capstone C3: the same engine, with A19's map for a solar farm.
The bench
| Control | Default plan | Range |
|---|---|---|
| Furnaces and resistance heat switched to heat pumps | 0 % | 0 to 100 %, in steps of 5 % |
| Buildings retrofitted | 0 % | 0 to 100 %, in steps of 5 % |
| Dense core's heat from a district network | 0 % | 0 to 50 %, in steps of 5 % |
| Network's heat pump | 0 MW heat | 0 to 250 MW heat, in steps of 10 MW heat |
| Network's heat store | 0 MWh | 0 to 2,000 MWh, in steps of 100 MWh |
| Cars that are electric | 1 % | 1 to 100 %, in steps of 1 % |
| EV charging | Unmanaged | one of: Unmanaged, Managed |
| Rooftop solar added | 0 MW | 0 to 400 MW, in steps of 10 MW |
| Batteries at the substations (4 hours) | 0 MW | 0 to 200 MW, in steps of 10 MW |
| Substation upgrades | Allowed | one of: Allowed, Not allowed |
| Upgrade cost | 800 $/kW | 200 to 2,000 $/kW, in steps of 50 $/kW |
| Heat a retrofit saves | 18 % | 10 to 50 %, in steps of 1 % |
| Retrofit cost | 9,000 $/home | 3,000 to 25,000 $/home, in steps of 500 $/home |
| Network cost | 12,000 $/home | 5,000 to 25,000 $/home, in steps of 500 $/home |
| Who adopts first | Every group alike | one of: Every group alike, Lower incomes first, Higher incomes first |
| Shared costs recovered | Per kWh | one of: Per kWh, Fixed charge, By income |
With JavaScript on, you change these, run the hub in your browser and copy a link to your plan. Prairie City is fictional; its numbers are illustrative.
- Illustrative: Prairie City, its districts, substation limits and household groups (prairie-city.json); retrofit, district-heat, store and upgrade costs are set for teaching, within ranges you can change.
- Assumed: the heat network's gas boiler already exists (fuel only); managed cars are plugged in whenever needed; the weather is NOAA's normals on SPP's 2025 days (synthetic).
- Based on public data: Kansas's 2025 prices (EIA), Wichita's weather normals (NOAA), SPP's 2025 hourly shapes (EIA-930), eGRID's 2023 SPP North CO₂ rate (EPA), DOE LEAD's income bands.
- Costs: 2025 dollars; heat pumps and rooftop solar from EIA, batteries from NREL, paid yearly at 4% real over each item's life.
Results
| Result: 2025 as it is, then "Electrify heat and cars" (80% of furnaces and resistance heat to heat pumps, half the cars electric) | Value |
|---|---|
| 2025 as it is: yearly cost against 2025 (2025 dollars; equipment and upgrades as yearly payments) | $0.0M |
| 2025 as it is: CO₂ of the three districts' buildings and cars | 1,921,977 t a year |
| 2025 as it is: busiest hour against the limit, core · suburbs · fringe | 213/250 · 192/230 · 48/60 MW |
| 2025 as it is: substation upgrades bought | 0 MW |
| 2025 as it is: energy burden, homes below 80% of area median income (screening estimate) | 6.1% |
| Electrify heat and cars: yearly cost against 2025 (2025 dollars; equipment and upgrades as yearly payments) | −$65.8M |
| Electrify heat and cars: CO₂ of the three districts' buildings and cars | 1,527,234 t a year |
| Electrify heat and cars: busiest hour against the limit, core · suburbs · fringe | 276/250 · 288/230 · 67/60 MW |
| Electrify heat and cars: substation upgrades bought | 91 MW |
| Electrify heat and cars: energy burden, homes below 80% of area median income (screening estimate) | 5.4% |
Precomputed with HiGHS on 6 November 2026: the hub as a linear program over eight representative days. Prairie City is fictional; its numbers are illustrative. With JavaScript on, the bench runs your own plan.
How the engine works, as diagrams
- The hub
- Each hour, electricity through the substation, gas and rooftop sun must meet each district's heat, base load and car charging; heat pumps, furnaces, a heat network, batteries and managed charging sit between.
- The limit
- Each substation's flow stays below its limit every hour, unless the plan buys more room; the busiest hour decides, not the year's total.
- It holds when
- Eight representative days stand for 2025, storage shifts energy only within a day, and 2025's prices, people and homes stay as they are.
- Who pays
- Bills and energy burden by household group come from an accounting layer after the LP, with a stated rule for who adopts first.
Go deeper · ModelerThe linear program behind the bench
M12 writes the hub down: building shares as decisions, the balance in each district-hour, the substation’s ceiling and its dual, and a CO₂ cap whose dual is the cost of the last tonne. Its notebook rebuilds the model in Python with SciPy and HiGHS. The capstone C3 plans the city to 2040 on this engine.
Go deeperWhen two answers cost the same: the tie rule
With one electricity price all day, many schedules cost the same: a car can charge at 01:00 or 03:00. Small stated costs, left out of every reported number, pick one:
- $20 a year per MW of each district's busiest hour, and $10 per MW of the three districts' busiest hour together: flexible loads spread out.
- $1 per MWh out of a battery and $0.50 per MWh out of the heat store: no cycling for nothing.
- $0.10 per MWh of managed charging, times the hour's share of SPP's peak demand: quieter hours first.
So the LP minimises the cost plus these small costs. On a few plans it pays a little to keep a busiest hour that is under its limit lower:
- The price of the ties: under $30 a year in the engine's test, against the cheapest schedule found without them.
- The same answer: every preset run again with the costs ×2 and ×0.1 gives the same numbers.
- One answer: each busiest hour, upgrade and the energy bought is the same over all plans within $1 of the best cost.
- Your plans: not checked this way; their hourly schedules can still differ.
Numbers, sources and what’s next
Inputs the engine uses
| Input | Value | Source |
|---|---|---|
| Substation limits: core · suburbs · fringe | 250 · 230 · 60 MW | prairie-city.json: each district's 2025 busiest hour × 1.15, rounded up to the next 10 MW (17%, 20% and 25% above it; teaching) |
| Electricity, Kansas 2025: homes · businesses | 14.44¢ · 11.19¢ per kWh | Electric Power Annual, Table 2.10: Average Price of Electricity to Ultimate Customers by End-Use Sector, by State, 2025 and 2024 (EIA) |
| Gas, Kansas 2025: homes · businesses | $14.81 · $11.90 per thousand cubic feet | Natural Gas Prices, Kansas (annual) (EIA) |
| Grid CO₂ | 862 lb per MWh, plus 5% losses | EPA eGRID2023, SPP North |
| Heat pump COP, an illustrative curve | 2.4 at −15 °C; 3.2 at 0 °C; 1 below −23 °C | anchored to DOE's cold-climate challenge target, 2.4 at −15 °C (U.S. Department of Energy, 24 Sep 2021); the rest is the course's curve (lesson F3), with resistance backup assumed below −23 °C |
| Heat pump, per home | $7,355, 15 years | EIA AEO2026, residential (2022 dollars, converted) |
| Rooftop solar | $4,738 per kW, 25 years | EIA AEO2026, residential (2022 dollars, converted) |
| Battery, 4 hours | $1,371 per kW, 15 years | NREL 2025 update (2024 dollars, converted) |
| Retrofit: cost a home · heat saved · life | $9,000 · 18% · 30 years | set for teaching (illustrative): the defaults, which you change on the bench |
| Heat network: per home-equivalent · plant heat pump · heat store | $12,000 (40 years) · $1,200 per kW of heat, COP 3 (25 years) · $3,000 per MWh (30 years) | set for teaching (illustrative); 10% of the heat lost in the pipes; the gas boiler (90%) is assumed to exist already: its fuel is counted, not its construction |
| Substation upgrade | $800 per kW, 40 years | set for teaching (illustrative): the defaults, which you change on the bench |
| Managed charging | any hours of the same day, at most a sixth of the day's charge in one hour | set for teaching: cars plugged in at home or work whenever needed (an upper bound on what managed charging can do) |
| Yearly payments | 4% real, over each item's life | lesson 13's rate (NLR ATB 2025) |
Keep going
Built on
Sources and further reading
- EIA. Electric Power Annual, Table 2.10: average price of electricity by state and sector, 2025.
- EIA. Natural Gas Prices, Kansas, 2025.
- EPA. eGRID summary data, eGRID2023 (revision 2): SPP North's CO₂ rate.
- EIA. Carbon Dioxide Emissions Coefficients.
- NOAA. U.S. Climate Normals 1991–2020: Wichita.
- DOE. Low-Income Energy Affordability Data (LEAD) Tool: income bands and the definition of energy burden.
- EIA. Assumptions to the Annual Energy Outlook 2026: Residential Demand Module, Tables 2–3 (heat pumps, rooftop solar).
- DOE (24 September 2021). Residential Cold-Climate Heat Pump Technology Challenge Specification, version 1.2: the COP 2.4 at −15 °C target the course's illustrative curve passes through.
- Cole, Ramasamy and Turan (2025). Cost Projections for Utility-Scale Battery Storage: 2025 Update. NREL/TP-6A40-93281.
- Tonn and others (2014). Weatherization Works: Summary of Findings from the Retrospective Evaluation of the U.S. Department of Energy's Weatherization Assistance Program. ORNL/TM-2014/338, Oak Ridge National Laboratory (pp. xiv and 12).
- Geidl and others (2007). Energy hubs for the future. IEEE Power and Energy Magazine 5(1), 24–30.
- HiGHS. Documentation of the open-source solver that runs the bench in your browser.
Spotted an error, or stuck? Write to hlli@ksu.edu. Corrections are made in place and dated here.