Small modular reactors for data centers

Cell Reports Sustainability (2026), Perspective, co-first author

Nuclear & data centers
What would it take for small modular reactors to power data centers, and which economic dimensions must a credible techno-economic assessment capture?
  1. Projects
  2. Nuclear & data centers

Co-first author

  • Perspective article
  • Techno-economic section
  • FOAK and NOAK costs
  • Reliability premium
  • Levelized cost of computing

Research question

What would it take for small modular reactors to power data centers, and which economic dimensions must a credible techno-economic assessment capture?

Key insight

Reliability requirements add a capital premium that levelized cost leaves out

A hyperscale campus needs Tier IV-level availability, so one reactor is not enough: with N+1 redundancy, a 300 MW campus may need 400 MW of SMR capacity. Standard levelized-cost estimates omit this reliability premium, so they understate the cost of firm on-site supply.

My contribution

Co-first author. Wrote the techno-economic analysis section, introduction and conclusions.

How I approached it

  1. ChallengePublished SMR cost figures mix first-of-a-kind budgets with long-run nth-of-a-kind targets.

    What I didI set first-of-a-kind and nth-of-a-kind capital costs of SMR projects side by side and argued that assessments treat them as separate cases, each with its own financing and risk.

    Why it matteredLong-run figures make first projects look more viable than they are, and early data-center buyers carry that risk.

  2. ChallengeLevelized cost of electricity leaves out cooling, which takes 30–40% of a hyperscale facility's energy.

    What I didIn the section I drafted, I proposed a service-based metric, the levelized cost of computing, which puts electricity and cooling costs over units of computing service.

    Why it matteredIt compares on-site nuclear, grid and renewable-plus-storage supply by what each delivers to the data center.

Method

Perspective synthesizing technology, economics and policy for SMR-powered data centers.

Key findings

  1. Data-center reliability requirements add a substantial premium to the capital cost of on-site nuclear supply.
  2. First-of-a-kind and nth-of-a-kind cost estimates for SMRs diverge widely, so assumptions must be explicit.
  3. Service-based metrics, such as cost per unit of computing, and co-products such as heat matter for comparisons.

Boundary conditions

A Perspective: it frames the questions and evidence rather than presenting a new case-study model.

What it led to

Pricing the heat used for cooling, hour by hour, became the core of my boundary analysis for one data-center campus. Small modular reactor cogeneration for a hyperscale data center

Publications

  1. Cell Rep. Sustain.
    The role of small modular reactors in powering data centers for a sustainable digital economy
    R. A. Jacob*, H. Li*, A. M. Rad, B. Poudel, Y. Li, M. Sun, T. R. McJunkin, J. Zhang
    Cell Reports Sustainability, vol. 3, article 100820, 2026. Co-first authors
    DOI PDF
    @article{jacob2026role,
      title     = {The role of small modular reactors in powering data centers for a sustainable digital economy},
      author    = {Jacob, Roshni Anna and Li, Honglin and Rad, Ali Mahboub and Poudel, Bikash and Li, Yaoyu and Sun, Mucun and McJunkin, Timothy R and Zhang, Jie},
      journal   = {Cell Reports Sustainability},
      volume    = {3},
      pages     = {100820},
      year      = {2026},
      publisher = {Elsevier},
      note      = {Co-first authors},
      doi       = {10.1016/j.crsus.2026.100820}
    }

Outputs

Paper (DOI) Paper (PDF)

Reproducibility

Not applicable (Perspective).

Last updated 2026-10

Previous projectSmall modular reactor cogeneration for a hyperscale data center Next projectData-center demand and the commercialization of small modular reactors

© 2026 Honglin Li · Kansas State University · hlli@ksu.edu

 

Last updated: November 2026 · Built with Quarto