Illustrative LCOEs from EIA plant assumptions and U.S. fleet averages (real 2025 dollars, $/MWh)
| Plant | Building the plant | Fixed upkeep | Fuel | Upkeep per MWh | LCOE |
|---|---|---|---|---|---|
| Onshore wind farm | 33.44 | 11.68 | 0.00 | 0.00 | 45.11 |
| Solar farm | 40.82 | 11.23 | 0.00 | 0.00 | 52.05 |
| Gas combined-cycle plant | 11.61 | 2.47 | 23.97 | 3.57 | 41.61 |
| Gas peaker | 56.21 | 6.03 | 35.20 | 4.17 | 101.60 |
With JavaScript on, you work through this in eight steps: predict, split the cost, discount, blend a WACC, find the price that pays back, use the calculator, read a tornado chart, and see when the energy arrives.
EIA and ATB inputs in real 2025 dollars, with no taxes, credits or grid costs, so not the agencies' own LCOEs; Prairie Town's plants are illustrative. Sources and dates: where the inputs come from.
Need a refresher? Toolbox K1 ($ per kW against $ per MWh) and K2 (fuel cost per MWh from a heat rate).
What you just did, as diagrams
- Four costs
- Building the plant, fixed upkeep, fuel and upkeep per MWh; wind and solar are mostly building cost, gas plants mostly fuel.
- Discounting
- Money later is worth less than money now, so future costs and sales are divided by (1 + r) for every year of waiting.
- WACC
- The blended rate a project pays its lenders and owners; it is the discount rate of the plant.
- Capital recovery factor
- The share of the building cost to repay each year so that it is paid off, with interest, over the plant's life.
- LCOE
- The steady price per MWh that repays every cost over the life: yearly costs divided by yearly MWh, plus fuel and upkeep per MWh.
- Tornado chart
- Each input swung from low to high, one at a time, to rank what moves the result over the chosen ranges.
- LCOE's blind spot
- It gives every MWh the same worth, whatever the hour; what one more MWh saves depends on the hour it arrives.
Go deeper · AnalystThe LCOE formula and the capital recovery factor
Paying off a building cost \(C\) ($/kW) with \(n\) equal yearly payments \(A\) at a real rate \(r\) means the payments’ present value equals \(C\):
\[C = \sum_{t=1}^{n} \frac{A}{(1+r)^t} = A\,\frac{1-(1+r)^{-n}}{r},\]
\[\text{so}\quad A = \frac{r}{1-(1+r)^{-n}}\, C = \mathrm{CRF}\cdot C .\]
When \(r = 0\) the capital recovery factor is simply \(1/n\).
Need a refresher? Toolbox K3 (discounting and the capital recovery factor).
The LCOE is the steady price at which the plant’s discounted sales repay everything, so its net present value is zero.
Each kW makes \(E = \mathrm{CF} \times 8{,}760 / 1{,}000\) MWh a year, with the capacity factor (lesson 5) as a fraction: 33.8% is 0.338.
\[\mathrm{LCOE} = \frac{\mathrm{CRF}\cdot C + \mathrm{FOM}}{E} + \text{fuel} + \mathrm{VOM}\]
Here fuel per MWh = heat rate (MMBtu per MWh) × gas price ($ per MMBtu).
Check it on the wind farm:
- \(\mathrm{CRF}(4\%, 30) = 0.0578301\);
- yearly cost: \(0.0578301 \times 1{,}712 + 34.57 = 133.58\) $/kW;
- yearly output: \(E = 0.338 \times 8.76 = 2.961\) MWh per kW;
- LCOE: \(133.58 / 2.961 = \$45.11\) per MWh.
The 2025 ATB writes the same equation with a fixed charge rate, \(\mathrm{FCR} = \mathrm{CRF} \times\) a factor for taxes and depreciation; here that factor is 1.
The WACC with taxes: loans’ share \(d\) at rate \(r_d\), owners’ money at \(r_e\) and tax rate \(\tau\) give \(d\,r_d(1-\tau) + (1-d)\,r_e\). Step 4 left the tax out.
A nominal rate \(n\) becomes real with \((1+n) = (1+r)(1+i)\), for inflation \(i\).
Go deeper · ModelerWhere LCOE's pieces go in a planning model
A capacity-expansion model can account for these costs directly, instead of comparing LCOEs.
It charges each kW it builds a yearly \(\mathrm{CRF}\cdot C + \mathrm{FOM}\), and every MWh its fuel and upkeep.
It chooses what to build and how to run it, hour by hour, in one optimization, so step 8’s timing problem is inside the model.
Capacity expansion with representative periods (M3, in the Modeler tier) uses exactly this yearly charge.
Techno-economic analysis inside an optimization model (M11) adds taxes, credits and a boundary choice.
Year-by-year cash flows, NPV, IRR and payback for one project are Analyst lesson A1.
Go deeperWhat this calculator leaves out
- Taxes, depreciation and tax credits: the agencies include them, so their LCOEs differ from these.
- Interest paid during construction, and the time a plant takes to build.
- Grid connection, new transmission, and the backup or balancing a variable plant may need.
- Output that falls as equipment ages, and costs that differ by region.
- Any change in costs over time: every input is one fixed number that you can move.
- Step 8 values each MWh at its hour's running cost of the last plant needed. A plant's worth also includes the capacity it offers at the peak.
- That hourly value is for one more MWh, not what a whole farm saves: growing solar from 200 to 400 MW cuts the day's running cost by $56,460, or $31.38 per added MWh.
- LCOE here is the cost per MWh a plant can make. When some of it is spilled, the cost per MWh actually used is higher.
Check yourself
Myth or fact? “The plant with the lowest LCOE is always the cheapest choice for the grid.”
- Myth
- Fact
Answer
Myth. LCOE leaves out when and where the MWh arrive: on Prairie Town's summer peak-demand day, a wind MWh was worth $56.35 on average and a solar MWh $50.27.
Myth or fact? “The discount rate is a technical detail that barely changes the answer.”
- Myth
- Fact
Answer
Myth. From 4% to 7% real, the wind farm's LCOE rises from $45.11 to $58.27 per MWh, by 29.2%.
Myth or fact? “A tornado chart shows how likely each outcome is.”
- Myth
- Fact
Answer
Myth. It shows how far the result moves over ranges someone chose, one input at a time; other ranges can change the ranking.
Myth or fact? “With the same building cost, a windier site gives a lower LCOE.”
- Myth
- Fact
Answer
Fact. The same yearly cost is spread over more MWh: at a 43% capacity factor instead of 33.8%, wind's LCOE falls from $45.11 to $35.46.
A plant's yearly repayment plus fixed upkeep is $130 per kW, and each kW makes 2.628 MWh a year (a 30% capacity factor). With no fuel and zero upkeep per MWh, what is its LCOE?
- $13.00/MWh
- $39.00/MWh
- $49.47/MWh
- $130.00/MWh
Answer
$49.47/MWh: 130 ÷ 2.628 = 49.47. Yearly cost per kW divided by yearly MWh per kW.
At 7% a year, what is $100 paid in 10 years worth today?
- $93.00
- $70.00
- $50.83
- $7.00
Answer
$50.83: 100 ÷ 1.07¹⁰ = 50.83. Each year of waiting divides by 1.07.
Numbers, sources and what’s next
Numbers to remember
| Number | What it means | Source |
|---|---|---|
| $1,712/kW | Building cost of a new onshore wind farm, before interest during construction (2025 dollars). | EIA, AEO2026 assumptions, Table 3 (PDF) · April 2026 |
| $1,032/kW | Building cost of a new gas combined-cycle plant (multi-shaft design), on the same basis. | EIA, AEO2026 assumptions, Table 3 (PDF) · April 2026 |
| 33.8% · 24.0% | Average capacity factors of U.S. utility-scale wind and solar photovoltaic generators in 2025. | EIA, Electric Power Annual, Table 4.08.B · final 2025 data, October 2026 |
| $3.85/MMBtu | Average cost of natural gas to U.S. power plants in 2025, per MMBtu; it was $7.21 in 2022 (in 2022 dollars). | EIA, Electric Power Annual, Table 7.4 · final 2025 data, October 2026 |
| 30 years | The cost recovery period behind both the 2025 ATB's and EIA's levelized costs. | NLR, 2025 ATB · September 2026; EIA, AEO2026 levelized costs (PDF) · April 2026 |
Next on the starter path
In the real world
A levelized cost and a system's cost can move in opposite directions.
A higher hydrogen price makes each kilogram worth more, so the optimizer builds a larger electrolyzer to capture more surplus wind.
The extra capacity runs fewer full-load hours, so the cost per kilogram, the levelized cost of hydrogen, goes up.
Yet the added hydrogen revenue lowers the net cost of the whole system.
The cost per kilogram and the system's cost move in opposite directions.
The full case: case file CF2 (when the cost per kilogram and the cost of the system disagree).
Case file CF7 (what waiting for a grid connection costs, and who pays).
Where the inputs come from
| Input | Source |
|---|---|
| Building cost, upkeep, heat rates (2025 dollars) | EIA, AEO2026 assumptions, Table 3 (PDF) · April 2026 |
| Capacity factors, 2025 | EIA, Electric Power Annual, Tables 4.08.A and 4.08.B · final 2025 data, October 2026 |
| Gas cost, 2025 | EIA, Electric Power Annual, Table 7.4 · final 2025 data, October 2026 |
| Rate and 30-year life, case without tax credits | NLR, 2025 ATB · September 2026 |
| Prairie Town's summer peak-demand day, 29 July 2025 | Southwest Power Pool shapes, EIA-930 (accessed 2 November 2026); the town's plants and running costs are illustrative |
Sources and further reading
- EIA (2026). Assumptions to the Annual Energy Outlook 2026: Electricity Market Module (PDF). Table 3: building cost, upkeep and heat rates.
- EIA (2026). Levelized Costs of New Generation Resources in the Annual Energy Outlook 2026 (PDF): LCOE beside a value measure (LACE).
- NLR (2026). 2025 Electricity Annual Technology Baseline: Equations and Variables; Financial Cases and Methods.
- EIA. Electric Power Annual: Table 4.08.A, Table 4.08.B (capacity factors) and Table 7.4 (fuel costs).
- Short, W., Packey, D. and Holt, T. (1995). A Manual for the Economic Evaluation of Energy Efficiency and Renewable Energy Technologies (PDF). NREL/TP-462-5173.
- Joskow, P. (2011). Comparing the Costs of Intermittent and Dispatchable Electricity Generating Technologies. American Economic Review 101(3).
- Li, H. et al. (2024). Towards sustainable integration: techno-economic analysis and future perspectives of Co-located wind and hydrogen energy systems. Journal of Mechanical Design 146(2), 020903.
Spotted an error, or stuck? Write to hlli@ksu.edu. Corrections are made in place and dated here.
Text licensed CC BY 4.0, code MIT: teachers and students may reuse and adapt it, with credit to Honglin Li.